Thursday, 22 November 2012

End week 6 and the extension is wrapped


End of week 6 and the wrap has been put on. The council need to inspect this which is due for Wednesday. After this the cladding will go on. 

You get a real sense of the rooms now that the cladding is on


Inside the house. That is sophies door and room & the play room in front.


The view from the windows in the toy room. I love that you can see the sky from the house.



Wednesday, 21 November 2012

Framing is Complete & Scaffolding up for wrapping


this is where they are jackhammering out the old driveway base. this will be grass


old entrance to the house that the previous owners didnt take out. maybe this will cause a headache dont know yet.

 roof frame and the scaffolding!! The council have inspected and we are ready to go with the wrapping of the house.

Owner inspection. all good




Monday, 19 November 2012

Builders putting the frame up. they put them together off site and it has been a quick process in getting them up. 






Thursday, 15 November 2012

Poppa Tom lays a perfect slab

Today Tom was on site to lay the concrete for the mid floor. We can now stand on the floor and see what view we will have from the kids bedrooms and it is awesome. Tom did a perfect job on the slab. Thanks so much Tom we really love it!


Pouring the concrete
Spreading the concrete 




The kids loved watching Poppa working on the house. 



Sorting the concrete for the steps to the play area


Wednesday, 14 November 2012

Its on like Donkey Kong!

So we had a delay waiting for the concrete beams to come but hey have arrived! Yay! They were installed last Thursday and today (Thursday) the mid floor has been blocked in to prepare for the concrete pour. Tom is coming down tomorrow to do the pour for us which is fab! 




Thursday, 1 November 2012

Day 17 week 3 - it is all taking shape!

The blocks are laid for the garage. 

View from over the road. Even replacing those rotten retaining beams has made a huge difference.

The planter box & where the wall is for the landing at the top of the entrance stairs.

All going well so far. the weather has been great and it is great to be able to see the plans taking shape. lachlan is loving all the rock debris everywhere and throwing it around.